The design and permitting for the restoration
of Milford Pond was initiated during
the month of September 1998. The project
engineering consultant, Baystate Environmental
Consultants, Inc. (BEC) began the acquisition
of background material and previous reports
regarding Milford Pond. Aerial photographs
of the pond from 1995 were obtained in
both photographic prints at 100-scale
and in digital format. On September 22,
Tom Jenkins, P.E. and Paul Davis, Ph.D.
conducted a detailed field review of
the pond and its vicinity. A vegetative
assessment of the pond was conducted
by Dr. Davis, and a sketch plan was prepared
from which the base vegetation plan has
been developed. Henry Papuga of the Milford
Water Company was interviewed at his
offices, and potential sediment disposal
sites were investigated.
In late September and October, BEC personnel
were on the pond conducting bathymetric
probings over the open-water portions
of the pond. Passage through the pond
was extremely difficult because of the
density of vegetation and the low water
level. Global positioning (GPS) was utilized
in the field survey efforts, which included
the surrounding vicinity of the pond
for reference and orientation. In November,
a meeting of the Milford Pond Restoration
Committee (MPRC) was held to discuss
and review the progress being made. The
history and past use of the pond was
discussed. BEC indicated that hydraulic
dredging will likely prove the preferred
dredging methodology, and a potential
containment area was identified adjacent
to the pond along Simmer Street. Background
data on this property was obtained and
the property was incorporated into the
conceptual designs for the dredging project.
In December, the MPRC traveled to Berlin,
CT to observe a large freshwater hydraulic
dredging project currently underway at
Silver Lake, which is owned and managed
by the CTDEP. The Silver Lake operation,
including the dredging, sediment containment,
and return water treatment facilities,
is of a scale similar to that required
at Milford Pond.
Preparation
of preliminary dredging designs and
containment facility layouts were fully
underway in December. The sediment
sampling and testing program was conducted
in the winter of 1998-00. The conceptual
design of the project was also advanced
during this period. A draft of the "Conceptual Dredging Program
for Milford Pond" was completed in February
and presented to the MPRC at a public
meeting held March 2, 1999 at Milford
Town Hall.
Several MPRC meetings were held in the
spring of 1999 to review the conceptual
dredging program and to review alternative
sites for the dredging containment basins.
The Environmental Notification Form (ENF)
was under preparation during these months,
and was reviewed by the MPRC in the summer.
Contact was made with the Massachusetts
National Heritage and Endangered Species
Program regarding the potential for state-protected
rare species in the vicinity of Milford
Pond. Additional parcels were investigated
for potential use as containment basin
sites. Further discussions were had with
the Milford Water Company regarding use
of their property along Dilla Street
as a possible containment site.
Revisions to the ENF forms issued by
MEPA in October of 1999 necessitated
the complete remake of the draft ENF.
The revised ENF document was submitted
to the Massachusetts Department of Environmental
Management in November and remains under
their review. Following receipt of MADEM's
comments, the ENF will be submitted to
the Executive Office of Environmental
Affairs for the mandatory environmental
review process.